Question:I’ve already created a Feasibility Study data submission in Queue Point. How do I create one for System Impact Study for the same project?
Answer:You can do this in one of two ways once logged into Queue Point:
1. Navigate to the Existing Requests tab, and find your project. There is a button under Actions to create a submission for the SIS phase.
2. On the Attachments tab under Generation Interconnection, click the green button that says System Impact Study. Select your queue number from the drop-down. If you do not see your queue number, you can select Not Listed and manually type it in; however, you will not be able to copy data over from your Feasibility Study data submission if you select Not Listed.
Note: If you’d like to copy over data from the Feasibility submission, make sure you’re using the same account as you did for Feasibility.
Queue Point Data FAQs
-
If my System Impact Study data is the same as my Feasibility Study data, do I still need to create an SIS data submission?
-
I’m trying to attach my required documents in Queue Point, but they are being rejected because the files are too large. What should I do?
-
I’ve already created a Feasibility Study data submission in Queue Point. How do I create one for System Impact Study for the same project?
-
What kind of dynamic model information do I need to submit for my project in the Queue Point System Impact Study data form?
-
Which dynamic models are considered acceptable?
-
Should my maximum fault current value be RMS or peak?
-
I'm locked out of my Queue Point account. What should I do?