Question:

I’ve already created a Feasibility Study data submission in Queue Point. How do I create one for System Impact Study for the same project?



Answer:

You can do this in one of two ways once logged into Queue Point:

1. Navigate to the Existing Requests tab, and find your project. There is a button under Actions to create a submission for the SIS phase.

2. On the Attachments tab under Generation Interconnection, click the green button that says System Impact Study. Select your queue number from the drop-down. If you do not see your queue number, you can select Not Listed and manually type it in; however, you will not be able to copy data over from your Feasibility Study data submission if you select Not Listed.

Note: If you’d like to copy over data from the Feasibility submission, make sure you’re using the same account as you did for Feasibility.



Queue Point Data FAQs
  1. If my System Impact Study data is the same as my Feasibility Study data, do I still need to create an SIS data submission?
  2. I’m trying to attach my required documents in Queue Point, but they are being rejected because the files are too large. What should I do?
  3. I’ve already created a Feasibility Study data submission in Queue Point. How do I create one for System Impact Study for the same project?
  4. What kind of dynamic model information do I need to submit for my project in the Queue Point System Impact Study data form?
  5. Which dynamic models are considered acceptable?
  6. Should my maximum fault current value be RMS or peak?
  7. I'm locked out of my Queue Point account. What should I do?