Question:
As a transmission equipment owner, which equipment requires eDART transmission outage tickets?

Answer:

PJM requires that Transmission Outage tickets must be submitted for all PJM tariff facilities and any equipment in the PJM Transmission Facilities list identified as a Reportable Transmission Facility (YES or LOW). Generation owners need to coordinate this outage information, including any subsequent changes, with their transmission owner and the TO will submit the eDART ticket on the GO’s behalf.



Transmission Outage Ticket FAQs
  1. How do I see the transmission outages that are shown on OASIS, in eDART?
  2. How long does a completed transmission outage remain on the OASIS Transmission Facilities Outage List before it is removed from the listing?
  3. How do I see transmission outages that were previously displayed in the OASIS Transmission Facilities Outage List but have since been completed and removed from this list?
  4. As a transmission owner, must I submit a transmission outage ticket through eDART for trippings?
  5. As a transmission owner, when should I use the “Informational/Hotline Work” checkbox?
  6. As a transmission owner, what should I do if I need to change a transmission outage ticket and it is locked?
  7. As a transmission owner, when should I use the Emergency checkbox?
  8. How are transmission lines arranged in the eDART database?
  9. As a transmission owner, what should I do if I need to put in a ticket but cannot find a certain piece of equipment in eDART?
  10. As a transmission owner, where do I go to find notifications of other companies’ transmission outages?
  11. As a transmission owner, once I acknowledge a transmission outage notification, how can I see it again?
  12. As a transmission owner, what should I do when I receive notification of transmission outages that I don’t want to know about?
  13. As a transmission owner, how can I view all the equipment that I am supposed to receive outage notifications for?
  14. As a transmission equipment owner, which equipment requires eDART transmission outage tickets?
  15. When do I need to verbally notify PJM of transmission outages?
  16. When will I receive verbal notification from PJM about submitted Outage Tickets?
  17. As a transmission owner, can I see a report of generation outages in my transmission zone?
  18. As a transmission owner, how do I access reactive capability information for units in my transmission zone?
  19. As a transmission owner, how do I view the reactive tickets for my zone?
  20. How should I submit an eDART ticket for a job that starts at midnight?
  21. As a transmission owner, what should I put in the Description of Work field?
  22. As a transmission owner, how can I get NERC TADS data to be sent to NERC from eDART?