In the report index, what do the suffixes (such as C or E) mean for each generator?
C = Capacity component of the project
E = Energy-only component of the project
BAT = Load component of a battery, if applicable
Other = These could be existing units, active long-term firm projects, or counter-flow components of confirmed long-term firm transactions.