Question:

I have questions about the study results in my report. What’s the best way to get information?



Answer:

Around the deadlines for Feasibility Study or System Impact Study reports, project managers and analysis engineers are focused on delivering reports to all customers on time. You may have already received your report, but staff may still be dedicated to completing reports for other customers up until the deadline. First, check the posted FAQs for information that may answer your questions, then contact your PJM project manager if needed. To ensure we can answer them most efficiently, please send an email to your project manager with your specific questions. Once all reports are completed, project managers will address your questions and contact you if further discussion is needed.



Feasibility Study and Impact Study Reports
  1. I have questions about the study results in my report. What’s the best way to get information?
  2. What is Commercial Probability?
  3. Can my project connect if the system upgrades in my report are not built yet?
  4. How is cost allocation calculated for network upgrades?
  5. Would downsizing my project reduce the network upgrade costs?
  6. Are network upgrade costs allocated to projects in prior queues?
  7. What does the "Type" column in the report index represent?
  8. What is the difference between Gendeliv MW Impact and Full MW Impact?
  9. Why are withdrawn or deactivated units highlighted in my report?
  10. How much can I reduce my project size by?
  11. Are projects allocated cost proportionally to their impact?
  12. What does the ID# represent in the overload section of the report?
  13. In the report index, what do the suffixes (such as C or E) mean for each generator?
  14. What is the significance of the Local Energy Deliverability section?