Question:

What is the significance of the Local Energy Deliverability section?



Answer:

Queue projects are not assigned upgrade costs for the identified potential congestion issues, but PJM Operations may curtain the project if the summer peak conditions are realized in “real-time” operations. If the queue project anticipates being curtained frequently, they can submit a merchant transmission project (Attachment S or EE) to reinforce the bulk electric system to alleviate the congestion constraint. From an analysis standpoint, potential congestion issues are identified by applying the full energy output of the queue project for single contingencies.



Feasibility Study and Impact Study Reports
  1. I have questions about the study results in my report. What’s the best way to get information?
  2. What is Commercial Probability?
  3. Can my project connect if the system upgrades in my report are not built yet?
  4. How is cost allocation calculated for network upgrades?
  5. Would downsizing my project reduce the network upgrade costs?
  6. Are network upgrade costs allocated to projects in prior queues?
  7. What does the "Type" column in the report index represent?
  8. What is the difference between Gendeliv MW Impact and Full MW Impact?
  9. Why are withdrawn or deactivated units highlighted in my report?
  10. How much can I reduce my project size by?
  11. Are projects allocated cost proportionally to their impact?
  12. What does the ID# represent in the overload section of the report?
  13. In the report index, what do the suffixes (such as C or E) mean for each generator?
  14. What is the significance of the Local Energy Deliverability section?